Maryland People's Counsel says data centers should be charged 100 percent of upfront network upgrade costs
Maryland Office of People's CounselMaryland's state utility consumer advocate, in a complaint filed with the Federal Energy Regulatory Commission
In a complaint against the regional grid operator PJM, the Maryland Office of People's Counsel argued that data centers should be charged the full upfront cost of the network upgrades they require, with crediting, as well as for their ongoing use of the transmission system.
“To avoid subsidization and ensure adequate cost recovery, data centers should be charged 100 percent of upfront network upgrade costs, with appropriate crediting, and also be charged for ongoing use of the system.”
Original text

Where this statement fits
Should Google have to pay the full cost of shared grid upgrades its data centers trigger?
On January 12, 2026, Google told Senators Elizabeth Warren, Chris Van Hollen and Richard Blumenthal that it pays for all the electricity its data centers use and that it, not local residents, pays for new grid infrastructure required for its growth. On January 22, Warren said that paying an electricity bill is different from fully covering the infrastructure upgrade costs of Google's data centers. An October 2026 report by the three senators said the companies, including Google, commit to paying for infrastructure that serves only their facilities but not the full cost of wider network upgrades. In June 2026, testimony filed for Google in a Virginia utility case recommended letting large customers voluntarily pay the full upfront cost of the substations that serve them. On July 31, Virginia regulators ordered Dominion Energy to develop a policy assigning data centers the cost of the transmission that connects them, and Appalachian Power says revenue from Google's new load in Botetourt County will cover $264 million in upgrades. The dispute is over whether Google should pay the full cost of the shared grid upgrades its data centers trigger, rather than leaving part of that cost with other customers.
Source and context
Original text
About this source
Complaint filed with the Federal Energy Regulatory Commission on May 7, 2026, asking it to change how PJM allocates transmission costs driven by data centers. The senators' October 2026 report cites it.
Before the quotation
The complaint, filed with the Federal Energy Regulatory Commission on May 7, 2026, asks it to change how PJM allocates the cost of transmission projects driven by data centers. Just before this heading, it cites a FERC commissioner's suggestion that "higher of" pricing could keep a large new load from directly raising transmission costs for other customers.
After the quotation
The complaint says the "but for" and "higher of" protections used for merchant generators should be adapted to data centers. It later argues that the relief is needed to carry out the Ratepayer Protection Pledge signed by major hyperscale data center developers. The senators' October 2026 report cites the complaint.
How this statement is classified
The label describes this statement's response within the context above.
Why this label?
The Maryland Office of People's Counsel says "data centers should be charged 100 percent of upfront network upgrade costs" to avoid subsidization, a full-cost charge it pairs with appropriate crediting and a charge for ongoing use of the system.
- Recorded on
- Published here
More from this case
Read the full caseGoogle objects to cost-shifting risks in MISO fast-track proposal
Google LLC
“The lack of cost shifting protections is especially concerning”Read statement
Warren and colleagues challenge shared-cost shifting
“But data center developers have refused to commit to shouldering the full costs of wider network upgrades incurred due to their data centers. Put another way, the companies commit to paying for infrastructure that solely benefits them, but dispute how much they should pay for shared infrastructure that is paid for by all ratepayers but was only built to accommodate the data center.”Read statement
Appalachian Power says other customers are not expected to pay for the $264 million in grid upgrades for Google's Botetourt data center
Appalachian Power
“In this case, the project adds a large new customer load, which is expected to bring in enough additional revenue to cover the cost of the transmission line and substation upgrades. Because the added revenue is expected to offset those costs, other customers are not expected to pay more because of this work”Read statement
Share or embed this statement
The embed keeps its attribution link to The Dispute Index. Credit the image to The Dispute Index and link to the statement page.
Cite this record
- Publisher
- The Dispute Index
- Title
- Maryland People's Counsel says data centers should be charged 100 percent of upfront network upgrade costs
- First published
- Last updated
- Permalink
- https://disputeindex.com/events/5585-in-a-complaint-against-the-regional-grid-operator
Last updated marks the most recent saved version of this published statement.
The Dispute Index. "Maryland People's Counsel says data centers should be charged 100 percent of upfront network upgrade costs". First published: 2026-10-11. Last updated: 2026-11-23. https://disputeindex.com/events/5585-in-a-complaint-against-the-regional-grid-operator