Piedmont Environmental Council says Virginia families should not subsidize transmission built to connect data centers
Piedmont Environmental CouncilVirginia conservation nonprofit and intervenor in Dominion Energy's transmission rate case, through its president, Chris Miller
Chris Miller, president of the Piedmont Environmental Council, an intervenor in the Dominion Energy case, said the commission's order set a precedent that Virginia families and small businesses should not subsidize transmission built solely to connect new data centers.
“The decision establishes an important precedent: Virginia families and small businesses should not subsidize transmission infrastructure built solely to connect new large-load data centers”
Reporting
Reporting

Where this statement fits
Should Google have to pay the full cost of shared grid upgrades its data centers trigger?
On January 12, 2026, Google told Senators Elizabeth Warren, Chris Van Hollen and Richard Blumenthal that it pays for all the electricity its data centers use and that it, not local residents, pays for new grid infrastructure required for its growth. On January 22, Warren said that paying an electricity bill is different from fully covering the infrastructure upgrade costs of Google's data centers. An October 2026 report by the three senators said the companies, including Google, commit to paying for infrastructure that serves only their facilities but not the full cost of wider network upgrades. In June 2026, testimony filed for Google in a Virginia utility case recommended letting large customers voluntarily pay the full upfront cost of the substations that serve them. On July 31, Virginia regulators ordered Dominion Energy to develop a policy assigning data centers the cost of the transmission that connects them, and Appalachian Power says revenue from Google's new load in Botetourt County will cover $264 million in upgrades. The dispute is over whether Google should pay the full cost of the shared grid upgrades its data centers trigger, rather than leaving part of that cost with other customers.
Source and context
Reporting
About this source
Virginia Mercury report, reprinted with permission by WTOP, on the State Corporation Commission's order in Dominion Energy's transmission rider case.
Archived copy (opens in a new tab)Reporting
About this source
E&E News report on the Virginia State Corporation Commission's order directing Dominion Energy to develop a tariff assigning more transmission costs to data centers.
Before the quotation
The Virginia Mercury reported that environmental groups welcomed the State Corporation Commission's order directing Dominion Energy to develop a policy assigning transmission costs to data centers and other large-load users. The Piedmont Environmental Council intervened in the case.
After the quotation
E&E News quoted Miller calling the order an important first step and saying it does not resolve who should pay for the billions of dollars in supplemental and regional transmission projects driven by data center growth.
How this statement is classified
The label describes this statement's response within the context above.
Why this label?
Piedmont Environmental Council president Chris Miller calls the commission's order an important precedent that "Virginia families and small businesses should not subsidize transmission infrastructure built solely to connect new large-load data centers". He is objecting to data centers' costs falling on other customers.
- Recorded on
- Published here
More from this case
Read the full caseGoogle objects to cost-shifting risks in MISO fast-track proposal
Google LLC
“The lack of cost shifting protections is especially concerning”Read statement
Warren and colleagues challenge shared-cost shifting
“But data center developers have refused to commit to shouldering the full costs of wider network upgrades incurred due to their data centers. Put another way, the companies commit to paying for infrastructure that solely benefits them, but dispute how much they should pay for shared infrastructure that is paid for by all ratepayers but was only built to accommodate the data center.”Read statement
Appalachian Power says other customers are not expected to pay for the $264 million in grid upgrades for Google's Botetourt data center
Appalachian Power
“In this case, the project adds a large new customer load, which is expected to bring in enough additional revenue to cover the cost of the transmission line and substation upgrades. Because the added revenue is expected to offset those costs, other customers are not expected to pay more because of this work”Read statement
Share or embed this statement
The embed keeps its attribution link to The Dispute Index. Credit the image to The Dispute Index and link to the statement page.
Cite this record
- Publisher
- The Dispute Index
- Title
- Piedmont Environmental Council says Virginia families should not subsidize transmission built to connect data centers
- First published
- Last updated
- Permalink
- https://disputeindex.com/events/5583-chris-miller-president-of-the-piedmont-environmental-council
Last updated marks the most recent saved version of this published statement.
The Dispute Index. "Piedmont Environmental Council says Virginia families should not subsidize transmission built to connect data centers". First published: 2026-10-11. Last updated: 2026-11-23. https://disputeindex.com/events/5583-chris-miller-president-of-the-piedmont-environmental-council